Spartanburg County gave NorthMark's $2.76 billion data center deal first reading Thursday, three days after it stalled. What it allows and what comes next.

Spartanburg County Council on Thursday gave first reading to a development agreement for the NorthMark data center at 4000 S. Pine St. The draft says the companies behind it plan to invest at least $2.76 billion.

The vote came at a special called meeting, three days after the same agreement stalled. At the council’s regular meeting Monday, nobody moved it forward.

Updated Nov. 7: County Council gave the NorthMark agreement second reading Nov. 3, with Monier Abusaft and Grant DeShields voting no. The AIB and Jones Road agreements also passed second reading. Final votes are expected Nov. 16. Read the latest.

The agreement needs two more readings and two public hearings before it is final. The latest draft is dated to take effect Monday, Nov. 16. The county has a County Council meeting scheduled that day.

How the vote went

The county posted the video of Thursday’s special meeting on its YouTube channel. Council Chairman Manning Lynch called a voice vote, and the ayes carried it.

Council member Monier Abusaft voted against it. He chairs the Public Safety and Judiciary Committee, which held the county’s two special hearings on data centers in September. Abusaft said he had talked directly with NorthMark. He said he did not believe the spirit of those talks had been kept. “I can’t vote for this,” he said, as the agreement stands. He added that his vote did not change his view that a community turns the industry away at its own peril.

Council member Grant DeShields said he had voted against data centers at every step except the original fee agreement. He said he would vote for this one because it gives council “a greater role” in how the site is run during and after construction. “This ain’t finalized,” he said.

Council member Paul Abbott said the protections in the draft grew out of about 10 hours of testimony at the September hearings. “I emphasize it is the first draft,” he said. “We have two more meetings to get through.”

Why it stalled Monday

The agreement was on the agenda for County Council’s regular meeting Monday, Oct. 19. The meeting video shows the economic development committee let it lie for lack of a motion.

Later in the meeting, Abusaft explained why. He said there was no motion and no second because council members “saw insufficient amount of protections” compared with what had been discussed. “We take the public health of our citizens seriously,” he said.

The draft that passed Thursday differs from Monday’s. Both are in the county’s agenda packets for Oct. 19 and Oct. 22.

Monday’s draft Thursday’s draft
Size “at least 450 MW” 457 MW
One-mile spacing County would not approve another data center within 1 mile Clause removed
Start date Left blank Nov. 16, 2026

What the agreement says

The Oct. 22 draft is between the county and two Delaware companies: Numara LLC, which owns the land, and Valara Holdings LLC, which leases it. The property’s plat was drawn “for Northmark Spartanburg,” according to the legal description attached to the agreement.

The draft describes:

  • about 293.6 acres at 4000 S. Pine St.
  • a data center of 457 megawatts, on which construction has already started
  • substations, on-site power generation and fuel lines, backup generators and battery storage
  • investment of at least $2,756,660,000 in real estate, machinery and equipment
  • a target of at least 27 full-time jobs, though missing it is not a default
  • a 10-year term that both sides can extend

In return, the county agrees that later county rules will not apply to the project except where state law allows. The draft says no future moratorium will apply to it.

The company must show the county it meets four tests, judged as if every neighbor were in a restrictive zoning district:

  • a light and glare plan, during and after construction
  • a noise plan under the county’s zoning ordinance
  • a noise study showing operating noise will not rise more than 10 decibels
  • a landscaping plan

The draft says the county has reviewed each one and found it sufficient. The dates the plans were submitted are left blank.

The company also agrees to hold a community meeting at least once a year. It will report its investment, jobs and water, power and gas demand to the county each year. Commercially sensitive parts of those reports would be kept confidential.

The air permit

The site already holds a state air permit. At a Sept. 21 special meeting of the Public Safety and Judiciary Committee, an environmental and regulatory lawyer who formerly worked at the South Carolina Department of Environmental Services presented on the project. She said the agency issued Synthetic Minor Air Construction Permit No. CP50000422 on Sept. 18. That is according to the minutes of that meeting.

The minutes say the agency received more than 350 public comments. Council members asked about formaldehyde, where background air readings were taken and how the agency enforces permits.

On Monday, County Council adopted a resolution asking the state agency to install an air quality monitor on the east side of the county. The resolution names the area south of U.S. 29, north of S.C. 9 and east of Old Peachtree Road. Abbott agreed with a colleague that the county has no authority over the agency.

The moratorium, and two other sites

All this sits inside the county’s data center moratorium, Ordinance O-26-26. On Monday, council reconsidered it, amended it and adopted it again on voice votes, according to the meeting video.

As read into the record, the amended moratorium:

  • pauses new data centers of 1 megawatt or more for 12 months from Sept. 21, 2026
  • exempts projects that already had a conditional plan approval, or a development permit issued in the 18 months before the moratorium
  • exempts data centers of 65 IT megawatts or less in a named industrial park or on a former industrial site
  • requires every exempt project to meet the light, noise and landscaping tests and sign a development agreement

Two other agreements were on Monday’s agenda.

  • 430 Jones Road. A data center of up to 65 IT megawatts on about 137 acres. The draft anticipates $1.5 billion in investment and at least 25 jobs. The chairman declared the ayes had it, the video shows.
  • 389 Tyger River Industrial Drive. A data center of up to 50 IT megawatts on about 16 acres for AIB CLT1 LLC, with $1.2 billion anticipated. The video does not make the outcome of that vote clear. The agreement went on to pass second reading Nov. 3.
Bar chart of anticipated investment in three Spartanburg County data center agreements: $2.76 billion at the NorthMark site at 4000 S. Pine St., $1.5 billion at 430 Jones Road and $1.2 billion at 389 Tyger River Industrial Drive.
Anticipated investment stated in each draft development agreement. Chart by Spartanburg Now
Share this chartFacebookWhatsAppX

What it means for you

  • To speak on the NorthMark agreement: state law requires two public hearings before the final vote. Watch the county agenda center for the dates. County Council’s Nov. 16 meeting will stream on the county’s YouTube channel.
  • If you live near industrial land: the moratorium still lets data centers of up to 65 IT megawatts go into named industrial parks and former industrial sites. Those projects must sign their own agreements, which come to council in public.
  • For background: read our story on the county’s trip to Loudoun County, Virginia, where council members studied how close data centers sit to homes. For zoning near you, see our guide to building permits and zoning.

The agreement is a Spartanburg County matter, decided by County Council under county land use rules. For city offices, see who to call at City Hall.