The Nov. 16 drafts add NorthMark's build schedule and site plan, plus screening and buffer rules for AIB and Jones Road. NorthMark names no community payment.

The pages that were blank when Spartanburg County Council gave three data center agreements their second vote are now filled in.

The completed drafts are in the county’s tentative agenda packet for Monday, Nov. 16. Council is set to hold a public hearing on each and give all three their third and final reading that night. The meeting starts at 5:15 p.m. in County Council Chambers at 366 N. Church St.

The three agreements cover:

  • NorthMark’s high-performance computing center at 4000 S. Pine St. (Numara LLC and Valara Holdings LLC)
  • AIB CLT1’s project at 389 Tyger River Industrial Drive
  • 300 Jones Road Associates’ data center on about 137 acres at or near 430 Jones Road

On Nov. 3, several exhibits read “To Be Inserted” or “To Come.” Speakers at that meeting asked council not to vote until they were complete. County staff said the finished pages would come out with the November tentative agenda, about 10 days before the vote. They have.

NorthMark: a schedule and a site plan

NorthMark’s agreement now carries a development schedule. Two data halls are being built inside the existing building. Two more would go in a new building to the west, with construction projected to start this month once permits are issued.

Table of NorthMark's data hall schedule at 4000 S. Pine St.: Data Halls 1 and 2 in the existing building, under construction, due January 2027 and June 2027; Data Halls 3 and 4 in a new building to the west, start projected November 2026, due June 2028 and December 2028.
NorthMark's development schedule from the Nov. 16 draft agreement. Graphic by Spartanburg Now
Share this chartFacebookWhatsAppX

The projected completion dates are:

  • Data Hall 1: January 2027
  • Data Hall 2: June 2027
  • Data Hall 3: June 2028
  • Data Hall 4: December 2028

The agreement says missing one of those dates is not, on its own, a breach. It would be “judged based upon the totality of the circumstances.”

The site master plan is an engineering drawing by Jacobs, marked preliminary. It shows four new buildings in the second phase, of about 423,000, 33,750, 19,450 and 18,000 square feet. It also shows a power yard, a substation lease area, a gas metering station and stormwater ponds. The drawing says the largest shift is expected to have up to 167 workers, with 307 parking spaces on site.

The agreement still sets a target of at least 27 full-time jobs and at least $2,756,660,000 in investment. It still names no community payment. The company’s yearly report to the county lists “community or charitable contributions, if applicable.”

Noise and lighting: the county says NorthMark complies

The NorthMark draft records that the company turned in its noise plan and a noise study on Oct. 28. The study used modeling to show that operating noise at set points would not rise by more than 10 decibels. The agreement says the county reviewed both and “acknowledges that this requirement is satisfied.”

It says the same of the company’s lighting plan and its landscaping plan, which was resubmitted Oct. 28. The draft notes that the noise study rule “was put into place after the Company had commenced construction.”

The agreement also says no later county rule or future moratorium applies to the project, except where state or federal law requires it.

AIB and Jones Road: what the design standards require

The AIB and Jones Road agreements now carry the same set of design standards. Among them:

  • Screening. Generators, cooling systems, substations, transformers and other ground equipment must be screened on all sides where they can be seen from a road or a home. Rooftop equipment needs a parapet or similar screen.
  • Fencing. Security fencing along roads must be wrought iron or ornamental metal picket in a dark finish. Barbed wire and razor wire are banned.
  • Buffers. A Type 5 buffer yard, as defined in the county’s zoning ordinance, is required along side and rear property lines. A lighter Type 2 buffer applies next to industry or a rail line with no homes beside it. No buffer is required next to another data center.
  • Trees. Internal drives need at least one canopy tree every 40 feet.
  • Walls. Building walls facing roads or homes must change material, pattern, texture or color at least every 150 feet.

Both agreements also say the companies will “promptly address noise complaints” by changing equipment or how the data center runs.

The payment schedules are unchanged from the Nov. 3 drafts:

Agreement Community payments
AIB CLT1 $6 million in year one, then $600,000 a year, $12.6 million over 12 years
300 Jones Road six payments of $1.5 million, $9 million in total

What it means for you

  • Read the agreements: the Nov. 16 agenda packet runs to 556 pages. The three data center agreements are near the end, under Old Business items T, U and V.
  • Track the votes so far: the county keeps them on its data center information page.
  • Speak: the public hearings on the three agreements come early in the meeting. The agenda allows 30 minutes in all and five minutes per speaker.
  • Watch: the county streams council meetings on its YouTube channel.

For how council voted on second reading and why three members said no, read our Nov. 3 story. For the background, see NorthMark’s first reading and our guide to building permits and zoning.