Spartanburg City Council unanimously approved the $18.2 million Morgan Square redesign and up to $19.75 million in hospitality-tax bonds Nov. 9. Work starts in early 2027.
Spartanburg City Council gave unanimous final approval Monday, Nov. 9, to the plan to enlarge and rebuild Morgan Square. The vote lets the city borrow up to $19.75 million for the work.
Updated Nov. 11: the city announced the outcome Nov. 10. This story now reports the final vote. Earlier versions said the result had not yet been posted.
The bonds will be repaid from the city’s hospitality tax, not property taxes. The vote authorizes city staff to move ahead with the estimated $18.2 million project, the city said. Council also approved the land exchange with the owner of One Morgan Square that lets Dunbar Street be realigned along the square’s northern edge.
Council passed the ordinance 7-0 on first reading Oct. 26, according to the draft minutes of that meeting. Construction is scheduled to begin in early 2027, the city said.
What the city plans to build
The city’s Morgan Square project page puts the current estimate at $18.2 million. The design, by Michael Vergason Landscape Architects, was presented to council Oct. 12. It will:
- make the square about 30% larger by realigning Dunbar Street
- take the square from 54 trees to 79
- turn the block of W. Main Street between Magnolia and Spring streets into permanent pedestrian space
- split the square into four spaces: Daniel Morgan Place, the Lawn, the Central Square and the Grove
- add an interactive fountain in the Central Square, a small stage in the Grove and a stone water wall facing Church Street
- create about 32,500 square feet of event space, with room for up to 2,500 people when Magnolia Street is closed
About 11 of today’s 54 trees, the willow oaks along Main Street, are expected to stay. About 43 will be removed and replaced, the city said. It said most of the removals are due to conflicts with underground stormwater pipes and the grade changes needed to make the square accessible. The city also plans to lease a storefront on the square for public restrooms, a visitor center and the downtown manager’s office. That lease has not been finalized.
Why the bond is bigger than the project
City Manager Chris Story explained the gap in a memo to council dated Oct. 23. He wrote that the city expects to borrow “very close to” the $18.2 million estimate. The higher $19.75 million ceiling covers the costs of issuing the bonds. Story said it also leaves room to decide whether other eligible projects, such as stage improvements at Barnet Park, should be financed at the same time.
The memo said the city is modeling an average interest rate of 5.19%. The real rate will not be known until the bonds are sold. The ordinance lets the city manager set the final amount, rates and repayment schedule, up to the $19.75 million cap.
How the city says it can pay for it
The hospitality tax is charged on sales of prepared food and drinks, mostly at restaurants. State law requires most of it to go to projects that draw visitors.
Story’s memo said the new payments fit without cutting existing programs because older obligations are ending:
- the city made the last payment on an earlier hospitality tax bond in fiscal 2025, freeing about $900,000 a year
- an obligation of about $500,000 a year ends in fiscal 2029
- one of about $300,000 a year ends in fiscal 2030
The memo said the city is also counting on growth in local restaurant sales. It said the city is “not relying on” any economic boost from the new square in its financial planning.
The bond ordinance lists three older hospitality-fee bonds still being repaid:
| Bond | Original amount | Still owed |
|---|---|---|
| Series 2016A | $4,005,000 | $1,160,000 |
| Series 2019 | $13,860,000 | $9,985,000 |
| Series 2021 | $3,520,000 | $1,420,930.70 |
The new bonds will share the same claim on hospitality fee revenue as those three.
The land swap with One Morgan Square
Realigning Dunbar Street needs land from the owner of the One Morgan Square office building on the north side of the square. Council approved an agreement 7-0 on Oct. 26 to trade triangular pieces of land with that owner, Opportunity Block LLC. Story’s memo on the swap said no money would change hands. The city’s project page says the added area would become part of the public square, owned and run by the city.
When work will happen
The city’s project page lists these target dates:
| Phase | Target |
|---|---|
| Storefronts and outdoor dining along the square | Begins early 2027; outdoor dining reopens by spring 2027 |
| W. Main Street, Magnolia to Spring | February to August 2027 |
| Main square | About 12 months, finishing spring 2028 |
The city said every business on the square will stay open to customers throughout construction. It said the city and its contractor will meet each business to set a regular schedule for updates.
Also on the Nov. 9 agenda
- Billboards. A resolution was also on the agenda to extend the city’s pause on new billboard applications, relocations and digital conversions until May 31, 2027, while the zoning code is rewritten. Council first approved the pause in December 2025, according to the city attorney’s request. The city has not yet posted the outcome of that vote.
- Code Spartanburg. Planning Director Fredalyn Frasier and consultant Caleb Raciot were scheduled to give an update on the zoning code rewrite.
- 2027 calendar. Council was set to approve its 2027 meeting dates.
What it means for you
- Property taxes do not change. The bonds are repaid from the hospitality tax on restaurant meals and prepared food, under the ordinance. See our property taxes page for what the city and county do charge.
- To speak at a future meeting, fill out the city’s public comment form by noon on the meeting day. Council next meets Dec. 14.
- Downtown will be a work zone in 2027. Expect fencing around the square from early 2027 and W. Main Street work from February to August. Our downtown Spartanburg guide and road construction page will carry the dates as the city confirms them.
The full agenda and attachments are on the city’s agendas and minutes page. Renderings, plans and answers to common questions are on the Morgan Square project page.